Projects Timeline
»detailed project schedule (.pdf)
January 2008
- Design- Northridge Elementary and Newton High School
February 2008
- Design- Northridge Elementary and Newton High School
March 2008
- Design- Newton High School
- Bid- Northridge Elementary
April 2008
- Construction- Northridge Elementary
- Design- Newton High School & Santa Fe Middle School
May 2008
- Construction- Northridge Elementary
- Design- Newton High School & Santa Fe Middle School
- Bid- Newton High School (Site Work)
June 2008
- Construction- Northridge Elementary
- Design- Newton High School & Santa Fe Middle School
- Bid- Newton High School (Boyd St. Paving- City)
July 2008
- Construction- Northridge Elementary & High School
- Design- Newton High School & Santa Fe Middle School
- Bid- Newton High School (Academic Bldg. Addition/Interior Remodel)
August 2008
- Construction- Northridge Elementary & High School
- Design- Newton High School & Chisholm Middle School
- Bid- Santa Fe Middle School
September 2008
- Construction- Northridge Elementary, High School & Santa Fe
- Design- Newton High School & Chisholm Middle School
October 2008
- Construction- Northridge Elementary, High School & Santa Fe
- Design- Newton High School & Chisholm Middle School
- Bid- Chisholm Middle School (Site Work)
November 2008
- Construction- Northridge Elementary, High School & Santa Fe
- Design- Newton High School & Chisholm Middle School
December 2008
- Construction- Northridge Elementary, High School, Santa Fe & Chisholm
- Design- Cooper Early Education Center
- Bid- Chisholm Middle School (Addition)
January 2009
- Construction- High School, Santa Fe, Chisholm & Demo- Cooper Annex
- Design- Cooper Early Education Center
February 2009
- Construction- High School, Santa Fe, Chisholm & Demo- Cooper Annex
- Design- Cooper Early Education Center
March 2009
- Construction- High School, Santa Fe, Chisholm & Demo- Cooper Annex
- Design- Cooper Early Education Center
April 2009
- Construction- High School, Santa Fe & Chisholm
- Bid- Cooper Early Education Center
May 2009
- Construction- High School, Santa Fe, Chisholm & Cooper
June 2009
- Construction- High School, Santa Fe, Chisholm & Cooper
July 2009
- Construction- High School, Santa Fe, Chisholm & Cooper
August 2009
- Construction- High School, Santa Fe, Chisholm & Cooper
September 2009
- Construction- High School, Chisholm & Cooper
October 2009
- Construction- High School, Chisholm & Cooper
November 2009
- Construction- High School, Chisholm & Cooper
December 2009
- Construction- High School, Chisholm & Cooper
January 2010
- Construction- High School & Cooper
February 2010
- Construction- High School & Cooper
March 2010
- Construction- High School & Cooper
April 2010
- Construction- High School & Cooper