January 2008

  • Design- Northridge Elementary and Newton High School

February 2008

  • Design- Northridge Elementary and Newton High School

March 2008

  • Design- Newton High School
  • Bid- Northridge Elementary

April 2008

  • Construction- Northridge Elementary
  • Design- Newton High School & Santa Fe Middle School

May 2008

  • Construction- Northridge Elementary
  • Design- Newton High School & Santa Fe Middle School
  • Bid- Newton High School (Site Work)

June 2008

  • Construction- Northridge Elementary
  • Design- Newton High School & Santa Fe Middle School
  • Bid- Newton High School (Boyd St. Paving- City)

 

July 2008

  • Construction- Northridge Elementary & High School
  • Design- Newton High School & Santa Fe Middle School
  • Bid- Newton High School (Academic Bldg. Addition/Interior Remodel)

August 2008

  • Construction- Northridge Elementary & High School
  • Design- Newton High School & Chisholm Middle School
  • Bid- Santa Fe Middle School

September 2008

  • Construction- Northridge Elementary, High School & Santa Fe
  • Design- Newton High School & Chisholm Middle School

October 2008

  • Construction- Northridge Elementary, High School & Santa Fe
  • Design- Newton High School & Chisholm Middle School
  • Bid- Chisholm Middle School (Site Work)

November 2008

  • Construction- Northridge Elementary, High School & Santa Fe
  • Design- Newton High School & Chisholm Middle School

December 2008

  • Construction- Northridge Elementary, High School,  Santa Fe & Chisholm
  • Design- Cooper Early Education Center
  • Bid- Chisholm Middle School (Addition)

January 2009

  • Construction- High School, Santa Fe, Chisholm & Demo- Cooper Annex
  • Design- Cooper Early Education Center

February 2009

  • Construction- High School, Santa Fe, Chisholm & Demo- Cooper Annex
  • Design- Cooper Early Education Center

March 2009

  • Construction- High School, Santa Fe, Chisholm & Demo- Cooper Annex
  • Design- Cooper Early Education Center

April 2009

  • Construction- High School, Santa Fe & Chisholm
  • Bid- Cooper Early Education Center

May 2009

  • Construction- High School, Santa Fe, Chisholm & Cooper

June 2009

  • Construction- High School, Santa Fe, Chisholm & Cooper

July 2009

  • Construction- High School, Santa Fe, Chisholm & Cooper

August 2009

  • Construction- High School, Santa Fe, Chisholm & Cooper

September 2009

  • Construction- High School, Chisholm & Cooper

October 2009

  • Construction- High School, Chisholm & Cooper

November 2009

  • Construction- High School, Chisholm & Cooper

December 2009

  • Construction- High School, Chisholm & Cooper

January 2010

  • Construction- High School & Cooper

February 2010

  • Construction- High School & Cooper

March 2010

  • Construction- High School & Cooper

April 2010

  • Construction- High School & Cooper