Cooper Early Education Center Construction Updates

construction
Cooper's construction blog

 

update 11-23-09

  • Reinforcing bars are in place for the footings and is ready for the pour.
  • Footings are being poured
  • Under slab plumbing is being installed
  • Transformer has been installed
  • under slab electrical connections are being installed into existing building


update 11-06-09

  • Dirt has been compacted for new building pad
  • Storm sewer system has been installed and is being completed
  • Footings have been poured around the SW corner of the addition
  • Fire lines have been installed
  • At the existing main entry, part of the concrete slab has been cut and removed for the new building connection.

update 10-24-09

  • Excavation is in progress
  • Dirt is being compacted for the new building pad
  • The storm sewer system installation is in progress.

update 10-07-09

  • Site work is in progress including soil excavation and reconditioning.
  • The southeast new parking lot driveway is complete.
  • The new walks and ADA ramps on the southwest corner of the site are complete.

update 9-17-09

  • The west entry ramps have been completed.
  • The concrete pad for the transformer is poured.
  • The sidewalk located southwest of the site has been removed and replaced with new sidewalk.
  • The southwest corner of the site is under construction to build the new landscaping and entrance into the parking.
  • Dirt is being compacted on the southeast corner of the site for the new entrance drive.
  • The new gas meter has been installed.

update 9-3-9

  • The west entrance is being excavated and the asphalt has been removed.

update  8-19-09

  • Playground equipment has been moved to the designated temporary location on the west site of the existing building.
  • Construction fence has been erected.
  • The annex building has been demoed and debris has been cleared.
  • Kansas Gas Company is currently working on the gas line.
  • A new fire hydrant has been installed at the south side of the site.
  • Stone columns at the south and west entrances have been dismantled and stored on site.