Northridge Elementary School Construction Updates
Ribbon-Cutting- January 2009
Moving Day
Kansan Article -January 9, 2009
November 3, 2008
- student lockers installed
- windows and double doors installed
- closet shelving installed
Visit Grogg's Blog for more details...
September 5, 2008
- all exterior brick work is finished
- plumbing is installed
- AC units are installed and ready to run
Visit Grogg's Blog for more details...
August 11, 2008
- roof is completely installed
- all mechanical work completed
Visit Grogg's Blog for more details...
July 25, 2008
- roofing materials installed
- interior walls framed
visit Grogg's Blog for more details...
July 18, 2008
- roofing materials are currently being installed
- metal studs and sheeting installed for exterior walls
- bases for A.C. units installed on roof
- footings dug for student benches outside classrooms
- ADA-compliant sidewalk poured for parking lot addition
visit Grogg's Blog for more details...
June 26, 2008
Visit Grogg's Blog for more details...
June 20, 2008
The concrete based is poured for the new addition and the parking lot addition is completed. Visit Grogg's Blog for more details...
June 3, 2008
Visit Grogg's Blog for more details...
May 20, 2008
Click on a thumbnail to see photos of what's been happening with construction at Northridge. The students have been very interested in all the dirt being brought in. For more details on this and other construction projects around the district, visit Grogg's Blog.
May 2, 2008
This morning students in Sue Gering's Kindergarten class got a close up view of the large earth moving equipment brought in recently.
Click on a thumbnail photo below to begin viewing the slideshow.
April 28, 2008
USD 373 hosted a community groundbreaking ceremony at Northridge Elementary School on April 28, 2008. The new 8700 sq. ft. addition will add six classrooms, along with bathrooms and storage space to the school. The Northridge addition is the first of six planned school expansion and remodeling projects, and is scheduled for completion by the end of 2008.
Photo Gallery
Representatives from the Newton Chamber of Commerce, the Cities of Newton and North Newton, the USD 373 Board of Education, and district staff along with Northridge students turned over dirt at the site of the Northridge school addition during a groundbreaking ceremony on April 28, 2008.
Click on a thumbnail photo below to begin viewing the slideshow.