Santa Fe Middle School Construction Updates
updates
July 24, 2008
Installation of ceiling tectum board, ductwork and bases for air conditioning units
June 26, 2008
Installation of ceiling insulation and access doors to roof.
June 3, 2008
Foam and wafer-board underlayment is laid in Lindley Hall to protect the gym floor prior to the installation of the air conditioning units. View Grogg's blog for this and other construction news.